Drammen

Felleskjöpet in Norway has expanded its facility in Drammen. The old receiving building has been rebuilt with two TGS intake pits, 7.5 meters long and 41 m3 each. On top of the house a silo package of 122m3 and a dryer are placed.

The dryer is a HR6-22-3 with heat recovery and dust control. To further reduce the dust impact on the environment the customer selected TORNUMs CDS, Centriclon Dust Separators, instead of standard fans. There are also silencers on the dryer to reduce noise. The heat source is a line burner, 3250kW, for LPG that can be converted for future natural gas. Transport equipment is Skandia H-Line,120 tons per hour.

The intake pits are equipped with four pit filters, five meters each, which collects dust when unloading grain.

  • Country: Norway
  • Category: Industrial
  • Type: Grain terminal
  • Status: Completed
Follow a project
2013-03-13
Existing intake house that will be partially demolished.
2013-03-13 Existing intake house that will be partially demolished.
2013-03-13
Beautiful view over Drammen from existing silo.
2013-03-13 Beautiful view over Drammen from existing silo.
2013-06-18
Demolition of the old house has begun.
2013-06-18 Demolition of the old house has begun.
2013-06-18
The new intake pits are assembled and are soon to be lifted in place.
2013-06-18 The new intake pits are assembled and are soon to be lifted in place.
2013-08-12
The rebuilding process has started.
2013-08-12 The rebuilding process has started.
2013-11-08
The concrete work is finished
2013-11-08 The concrete work is finished
2013-11-25
The silo package is lifted in place by a crane.
2013-11-25 The silo package is lifted in place by a crane.
2013-11-25
The dryer appears to the right of the silos.
2013-11-25 The dryer appears to the right of the silos.
2014-01-20
Intake pit filters improves the environment of the intake.
2014-01-20 Intake pit filters improves the environment of the intake.
2014-01-20
Final assembly of the dryer.
2014-01-20 Final assembly of the dryer.
2014-01-20
Final assembly of the dryer.
2014-01-20 Final assembly of the dryer.
2014-01-20
Ongoing installation of a 48 meter high elevator that takes the grain from the dryer to storage in existing concrete silo.
2014-01-20 Ongoing installation of a 48 meter high elevator that takes the grain from the dryer to storage in existing concrete silo.
2014-06-16
The dryer is fully assembled and only walls remains.
2014-06-16 The dryer is fully assembled and only walls remains.
2014-06-16
The dryer is fully assembled and only walls remains.
2014-06-16 The dryer is fully assembled and only walls remains.
2014-06-16
Filter suction at the intake pit with plastic shutters to further prevent dust spread.
2014-06-16 Filter suction at the intake pit with plastic shutters to further prevent dust spread.
2014-06-16
Elevator and platform are ready-made.
2014-06-16 Elevator and platform are ready-made.
2014-06-16
Inlet to concrete silo from the new conveyor.
2014-06-16 Inlet to concrete silo from the new conveyor.
2014-06-16
Inlet to concrete silo from the new conveyor.
2014-06-16 Inlet to concrete silo from the new conveyor.
2015-08-12
The building is ready.
2015-08-12 The building is ready.