Hörby Lantmän

Hörby Lantmän will expand the existing facility with a new building containing grain drying, intake and unloading, outdoor silos for grain storage and a Grain Cooler. The new grain facility will be docked together with the existing facility, delivered by TORNUM eight years ago. Storage silos are built for both wet grain and final storage of grain. The dryer is a continuous dryer, HR6, with heat recovery and has a capacity of 52 tons/h when drying grain from 19% to 15% with 85°C drying temperature. The heat source is direct gas. The Grain Cooler type TORNUM TGC100, will be used to cool wet grain prior to drying and dried grain that will be stored in the silos.

 

Watch a movie from the  project.

  • Country: Sweden
  • Categories: Industrial
  • Type: Grain terminal
  • Status: Finished
Follow the contruction
Drawing of the project.
Drawing of the project.
2014-02-11
Preparatory work for moving the the existing pond.
2014-02-11 Preparatory work for moving the the existing pond.
2014-02-19
Excavation work.
2014-02-19 Excavation work.
2014-02-24
Rickard Johansson, project manager at TORNUM, inspects the work performed.
2014-02-24 Rickard Johansson, project manager at TORNUM, inspects the work performed.
2014-02-28
Concrete work in progress.
2014-02-28 Concrete work in progress.
2014-02-28
Concrete work in progress.
2014-02-28 Concrete work in progress.
2014-03-06
Moulding of walls.
2014-03-06 Moulding of walls.
2014-03-06
Moulding of walls.
2014-03-06 Moulding of walls.
2014-03-17
View from the existing silo..
2014-03-17 View from the existing silo..
2014-03-20
Pre-assembly of the receiving pit and dryer.
2014-03-20 Pre-assembly of the receiving pit and dryer.
2014-03-20
The walls of the elevator shaft is finished and soil reconsolidation has begun. Reinforcement for the receiving pit are ongoing in parallel.
2014-03-20 The walls of the elevator shaft is finished and soil reconsolidation has begun. Reinforcement for the receiving pit are ongoing in parallel.
2014-03-24
The fans are assembled on the dryer
2014-03-24 The fans are assembled on the dryer
2014-04-01
The drying sections are pre-assembled and ready to be assembled.
2014-04-01 The drying sections are pre-assembled and ready to be assembled.
2014-0401 The hoppers under the bulk loading bins are assembled.
2014-0401 The hoppers under the bulk loading bins are assembled.
2014-04-01
The intake pit is in place.
2014-04-01 The intake pit is in place.
2014-04-01
The elevator shaft.
2014-04-01 The elevator shaft.
2014-04-08
The base plate has been reinforced.
2014-04-08 The base plate has been reinforced.
2014-04-15
The framework is welded together.
2014-04-15 The framework is welded together.
2014-04-15
Licenced welder in action
2014-04-15 Licenced welder in action
2014-04-15
Preparation prior to casting and assembly of potential equalization.
2014-04-15 Preparation prior to casting and assembly of potential equalization.
2014-04-15
Preparation prior to casting and assembly of potential equalization.
2014-04-15 Preparation prior to casting and assembly of potential equalization.
2014-04-22
The concrete plate for the drying house is ready.
2014-04-22 The concrete plate for the drying house is ready.
2014-04-22
Reinforcement of the concrete plate for the hopper silos has started.
2014-04-22 Reinforcement of the concrete plate for the hopper silos has started.
2014-04-22
The assembly of the roof has begun.
2014-04-22 The assembly of the roof has begun.
2014-04-24
The assembly of the roof is ongoing.
2014-04-24 The assembly of the roof is ongoing.
2014-04-24
The reinforcment of the concrete plate is finished.
2014-04-24 The reinforcment of the concrete plate is finished.
2014-04-24
The silos are delivered and will soon be assembled.
2014-04-24 The silos are delivered and will soon be assembled.
2014-04-28
The stands to the hopper silos is ready.
2014-04-28 The stands to the hopper silos is ready.
2014-04-28
Meeting with the companies involved to ensure that the construction work proceeds as planned.
2014-04-28 Meeting with the companies involved to ensure that the construction work proceeds as planned.
2014-04-28
The site seen from above.
2014-04-28 The site seen from above.
2014-04-30
The service platforms in the drying house is assembled..
2014-04-30 The service platforms in the drying house is assembled..
2014-05-05
The cylinder to the first hopper silo is assembled.
2014-05-05 The cylinder to the first hopper silo is assembled.
2014-05-06
The cylinder was planned to be lifted in place but the lift is canceled due to strong wind.
2014-05-06 The cylinder was planned to be lifted in place but the lift is canceled due to strong wind.
2014-05-06
The cylinder is temporarily anchored in the ground because of safety reasons.
2014-05-06 The cylinder is temporarily anchored in the ground because of safety reasons.
2014-05-06
Preparing prior to the sheet metal cladding.
2014-05-06 Preparing prior to the sheet metal cladding.
2014-05-08
The roof is in place...
2014-05-08 The roof is in place...
2014-05-08
....and the cylinder as well.
2014-05-08 ....and the cylinder as well.
2014-05-12
The cylinder to the second hopper silo is ongoing.
2014-05-12 The cylinder to the second hopper silo is ongoing.
2014-05-12
The discharge section of the dryer is lifted on its place in the house.
2014-05-12 The discharge section of the dryer is lifted on its place in the house.
2014-05-12
Further drying sections is lifted in place. The silo cylinder is soon ready.
2014-05-12 Further drying sections is lifted in place. The silo cylinder is soon ready.
2014-05-12
Further drying sections is lifted in place. The silo cylinder is soon ready.
2014-05-12 Further drying sections is lifted in place. The silo cylinder is soon ready.
2014-05-12
Further drying sections is lifted in place. The silo cylinder is soon ready.
2014-05-12 Further drying sections is lifted in place. The silo cylinder is soon ready.
2014-05-12
The work with concrete plate under the storage silos has started.
2014-05-12 The work with concrete plate under the storage silos has started.
2014-05-15
The catwalk over the hopper silos is currently assembled and the hopper under the cylinder is on its place. All drying sections is assembled and the bulk loading bins is also on place.
2014-05-15 The catwalk over the hopper silos is currently assembled and the hopper under the cylinder is on its place. All drying sections is assembled and the bulk loading bins is also on place.
2014-05-15
The work with the concrete plate for the storage silos is in progress in parallel.
2014-05-15 The work with the concrete plate for the storage silos is in progress in parallel.
2014-05-19
The embedded parts is in place and it is time for casting.
2014-05-19 The embedded parts is in place and it is time for casting.
2014-05-23
The cleaning- and grading machine has been delivered.
2014-05-23 The cleaning- and grading machine has been delivered.
2014-05-23
The concrete plate is ready.
2014-05-23 The concrete plate is ready.
2014-05-26
The assembly of one silo has started.
2014-05-26 The assembly of one silo has started.
2014-06-02
The site seen from above.
2014-06-02 The site seen from above.
2014-06-02
The first silo is ready and the second silo is currently assembled.
2014-06-02 The first silo is ready and the second silo is currently assembled.
2014-06-02
In the right corner you see four plinths for a tower, a support to catwalk and top conveyor.
2014-06-02 In the right corner you see four plinths for a tower, a support to catwalk and top conveyor.
2014-06-04
The roof is lifted in place.
2014-06-04 The roof is lifted in place.
2014-06-04
Ready!
2014-06-04 Ready!
2014-06-05
The aeration for the hopper silos is assembled.
2014-06-05 The aeration for the hopper silos is assembled.
2014-06-05
The cleaner stand is ready and the machine is lifted in place.
2014-06-05 The cleaner stand is ready and the machine is lifted in place.
2014-06-16
The catwalk over the storage silos is ready.
2014-06-16 The catwalk over the storage silos is ready.
2014-06-16
The top conveyor is assembled on the catwalk.
2014-06-16 The top conveyor is assembled on the catwalk.
2014-06-16
The support tower for the catwalk from the existing building is ready.
2014-06-16 The support tower for the catwalk from the existing building is ready.
2014-06-16
The outer aeration system is currently assembled.
2014-06-16 The outer aeration system is currently assembled.
2014-06-16
The doors to the intake is in place.
2014-06-16 The doors to the intake is in place.
2014-07-30
The plant is ready to take into operation.
2014-07-30 The plant is ready to take into operation.
2014-07-30
 The plant is ready to take into operation.
2014-07-30 The plant is ready to take into operation.