Lähteenmäki is a farm in northern Satakunta, Finland. The drying house from Tornum will be built summer 2015.  The project consists of a TS3-10-6 batch dryer, 870 kW oil furnace, ST and UT storage and a TGS intake pit. The transport capacity is 100  /h and total storage capacity 500 m3.

  • Country: Finland
  • Categories: Agriculture
  • Type: Drying and storage plant
  • Capacity: Total storage capacity 500 m3
  • Status: Finished
Follow the contruction
2015-03-06
A first site visit.
2015-03-06 A first site visit.
2015-04-21
The grain storage have been pre-mounted on the ground during the winter.
2015-04-21 The grain storage have been pre-mounted on the ground during the winter.
2015-04-21
The grain storage have been pre-mounted on the ground during the winter.
2015-04-21 The grain storage have been pre-mounted on the ground during the winter.
2015-04-21
The ground work has begun.
2015-04-21 The ground work has begun.
2015-04-21
The ground work has begun.
2015-04-21 The ground work has begun.
2015-05-27
The pre-mounted storage bins are lifted in place.
2015-05-27 The pre-mounted storage bins are lifted in place.
2015-06-01
The bulk loading bings are mounted and in place. The asembly of the roof has started.
2015-06-01 The bulk loading bings are mounted and in place. The asembly of the roof has started.
2015-06-01
The bulk loading bings are mounted and in place.
2015-06-01 The bulk loading bings are mounted and in place.
2015-06-12
Roof lifting in progress. The weather is ideal, just a small breeze.
2015-06-12 Roof lifting in progress. The weather is ideal, just a small breeze.
2015-06-12
Roof lifting in progress. The weather is ideal, just a small breeze.
2015-06-12 Roof lifting in progress. The weather is ideal, just a small breeze.
2015-06-30
The outside of the building is ready. CMT furnace is installed in the house.
2015-06-30 The outside of the building is ready. CMT furnace is installed in the house.
2015-06-30
The outside of the building is ready. CMT furnace is installed in the house.
2015-06-30 The outside of the building is ready. CMT furnace is installed in the house.
2015-09-09
Everything is ready and the dryer is ready to start drying grain.
2015-09-09 Everything is ready and the dryer is ready to start drying grain.
2015-09-09
Det första lasset med spannmål tippas i gropen.

The first grain is filled into the pit.
2015-09-09 Det första lasset med spannmål tippas i gropen. The first grain is filled into the pit.