S.A. Nidera Romania SRL

  • Heat recovery dryer HR6-27-4 with dust control
  • Storage capacity of 18 000 ton
  • Two buffer silos for wet product – 300 ton each
  • Conveying capacity 150 t/h commercial range
  • Industrial pre-cleaner with horizontal vibrating sieves and air aspiration
  • The system offers the possibility to load both trucks and barges
  • Two reception pits for truck
  • Flow scale
  • Computerized monitoring of temperatures

 

 

  • Country: Romania
  • Categories: Industrial
  • Type: Drying and storage plant
  • Capacity: Total storage capacity 18 000 tons
  • Status: Finished
Follow the contruction
Heat Recovery Dryer HR6-27-4
Heat Recovery Dryer HR6-27-4
2015-07-06
The foundation work have started.
2015-07-06 The foundation work have started.
2015-07-06
The foundation work have started.
2015-07-06 The foundation work have started.
2015-08-04
Assembly of the roofs of the two first storage silos.
2015-08-04 Assembly of the roofs of the two first storage silos.
2015-08-11
Assembly work on the silos continues. The first silo is ready to lift.
2015-08-11 Assembly work on the silos continues. The first silo is ready to lift.
2015-08-24
The first silo is lifted.
2015-08-24 The first silo is lifted.
2015-09-16
Assembly of the silo continues. Two of the silos have been erected.
2015-09-16 Assembly of the silo continues. Two of the silos have been erected.
2015-09-16
Assembly of the silo continues. Two of the silos have been erected.
2015-09-16 Assembly of the silo continues. Two of the silos have been erected.
2015-10-21
The flow scale is in its position.
2015-10-21 The flow scale is in its position.
2015-10-21
The assembly of the dryer has begun.
2015-10-21 The assembly of the dryer has begun.
2015-10-21
The assembly of the dryer has begun.
2015-10-21 The assembly of the dryer has begun.
2016-01-12
The assembly of the dryer is almost finished.
2016-01-12 The assembly of the dryer is almost finished.
2016-01-12
The catwalk towards the Danube river has been built.
2016-01-12 The catwalk towards the Danube river has been built.
2016-01-13
The barge loading chute has been placed in it’s final position.
2016-01-13 The barge loading chute has been placed in it’s final position.
2016-03-01
The mechanical assembly of the project is complete. The electrical installation continues.
2016-03-01 The mechanical assembly of the project is complete. The electrical installation continues.
2016-08-19
The plant is ready and in use.
2016-08-19 The plant is ready and in use.